www.brownfieldslawyer.com

REVISION OF MASSACHUSETTS ENVIRONMENTAL POLICY ACT REGULATIONS NOW EFFECTIVE

By: Marilyn L. Sticklor, Esq.

The long-awaited revisions to the Massachusetts Environmental Policy Act became effective on July 1, 1998. These revisions resulted from the efforts of an Advisory Committee, consisting of representatives of the public sector, private sector and public interest groups, which began its work in early 1997.

Background.

In recent years, the Massachusetts development climate has been criticized by the business community for the length and the duplication of efforts of its permitting process. Most maligned has been the Massachusetts Environmental Policy Act (commonly referred to as “MEPA”) process. The concept of the MEPA process is that environmental review should be coordinated in a single state office with particular environmental expertise. However, in practice, the MEPA process has been perceived as often being triggered by projects which did not have significant environmental impacts and as often requiring studies beyond those relating to state permits or funding. If the MEPA process were involved, the common experience was that six to nine months would be added to the development schedule for a project, adding expense and putting Massachusetts at a competitive disadvantage for development.

Highlights of the Revised MEPA Regulations.

In general, the development community will welcome the revised MEPA regulations.

The remaining situation in which a permit or other state action may not specifically relate to a threshold, however, is projects altering significant areas of land (at least 50 acres) or creating significant new impervious area (at least 10 acres) and projects within an Area of Critical Environmental Concern. For these projects, EIRs are required even if the project does not exceed any threshold relating to a particular permit or other state action. ENFs also must be filed if a project alters more than 25 acres of land or creates more than 5 acres of impervious surface even if the project does not exceed any other threshold relating to a particular permit or other state action.

New Procedures of which to be Aware.

The new regulations provide for expiration of MEPA approvals, and will not allow a Notice of Project Change to be filed for a stale project. If more than three years pass between the notice of availability of an EIR and commencement of a project, a Notice of Project Change must be filed. If more than five years pass, the MEPA process must be repeated by filing a new ENF. Rights in the MEPA process also are lost in certain cases if construction is suspended for more than three years, or if major steps in non-construction activities are discontinued.

Transition Rules.

After their effective date, the new regulations will apply to all projects, even those for which an ENF previously has been filed, with two exceptions. First, projects for which an ENF has been filed will continue to be subject to the thresholds of the old regulations. Second, the provision requiring a new ENF for lapse of time will not apply to projects for which MEPA filings have been made until one year after the effective date of the new regulations.

Practice Tips.

Developers will be well-advised to consider the following practice tips.

See the resume of Marilyn L. Sticklor: Resume


Home


Webmaster: goldberg@bostonlawfirm.com


Copyright © 1998, Alan S. Goldberg, All Rights Reserved.

Last revision: 7/8/98